Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following is the cost-effective rule for shortening a project?

 A. Crash the tasks with lowest cost. B. Crash the tasks with highest cost. C. Crash the non-critical tasks. D. Crash the critical tasks.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/03/14
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Crash the critical tasks.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option D is the best choice.

Abiodun Joda
by Abiodun Joda , office manager , Tola Joda Innovations

The cost effective rule for shortening a project is crash the non-critical tasks.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.