ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

During testing, multiple defects were identified in a product. The project manager overseeing this product's development can best use which tool to help prioritize the problems?

tool to help prioritize the problems?

A. Pareto Diagram

B. Control Chart

C. Variance Analysis

D. Order of Magnitude estimate

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/06/04
Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

...........A. Pareto Diagram,,,,,,,,,,,

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

A. Pareto diagram,Thanks.................

Ramzi SAMRI
من قبل Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

In this step, pareto diagram is the efficient solution

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

For prioritizing the defects, Pareto diagram is the right answer

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option A

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟