ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0?

A) The project has been cancelled while it was executed. At that time the project was   behind schedule and on budget.  

B) The project's deliverables have all been finished. The project came in behind schedule but on budget.  

C) The project's deliverables have all been finished. The project came in ahead of schedule but on budget.  

D) The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

 

user-image
تم إضافة السؤال من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
تاريخ النشر: 2016/08/15
Ahmed Hassan
من قبل Ahmed Hassan , Service Delivery Manager , Goodnews4me

Answer is A

 

SPI is 0.7 that means all the planned work has not been finished.....

EV is less than PV.....

.there is no information about the status of deliverables so all other options don't make sense...

Yahya Bah
من قبل Yahya Bah , Principal & Marketing Consultant , International Community

Schedule performance Index (SPI) and Cost performance Index(CPI). SPI being 0.7 means the project got completed only 70% of the planned portion in the scheduled time. This means that the planned work falls short of schedule. CPI = 1 means the Earned Value and Actual Cost incurred are equal hence the project is on budget.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B) The project's deliverables have all been finished. The project came in behind schedule but on budget. 

Mousab Al Nokkari
من قبل Mousab Al Nokkari , Engineering Manager , Al Majaz Engineering Consulting Office

 

Thanks for invitation ,,

 

SPI is 0.7 that means all the planned work has not been finished.

 

EV is less than PV, and the question says that it is a closed out project.

 

So the correct answer is A:

 

A) The project has been cancelled while it was executed. At that time the project was   behind schedule and on budget.

 

With Best Regards

Shiva Gadepalli
من قبل Shiva Gadepalli , Lead Consultant , A & A Business Consulting Pvt Ltd

It's a positive on the outlook! Only 70% of the work has been completed with 100% return assurance. But that doesn't mean the project is fulfilled. Critical parameters in completing the remaining 30% of the project need to be accounted to prevent negative fallout. Generally such a situation apparently seems comfortable but this is where most projects fail, if not carefully handled. This is by norm the 'handing over' period!

Mohammed Noser
من قبل Mohammed Noser , Civil Engineer , aalbwardi.com

ANSWER A  OR D IS THE SAME ANSWER

Ahmed Taha
من قبل Ahmed Taha , Digital Director , Home of Performance

It is not in my specialty. You probably need to ask someone who has an experience related 

sadia masood
من قبل sadia masood , Principal , Bahria Foundation

The project has been cancelled while it was executed.

At that time the project was behind schedule and was on the budget.

 But it was Okay on the budget.

Ashraf Kotb Ahmed
من قبل Ashraf Kotb Ahmed , Senior Service Delivery Manager , Microsoft Corporation

As this is the final SPI, not an interim one, this means that not all project deliverables have been delivered. So the only answer that makes sense is A

 

A) The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.  

Rafiq Irman
من قبل Rafiq Irman , Cost Control & Commercial , McConnell Dowell SEA

project was delayed from the target but cost within the plan budget

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟