Can anyone help me to troubleshoot the problem in SAP PS Module? Project Builder Cost and the Cost showing in reports are different.

Eg. In Project Buider, Cost is100,0 but when i check in CN41 transaction, reports showing different figure250,0 in WBS level but in activity it showing only100,0. How to troubleshoot this?

user-image
تم إضافة السؤال من قبل ASARUDEEN SOWKATH ALI , Planning Manager , Alfanar Construction
تاريخ النشر: 2014/02/11
ASARUDEEN SOWKATH ALI
من قبل ASARUDEEN SOWKATH ALI , Planning Manager , Alfanar Construction

Thanks for your reply Mr.Joefil, i mean here only budget not actuals. I have assigned one activity (A) under WBS-01, considered the Budgetted cost for the activty in Project Cost Plan as100 bucks and please note that WBS-01 has only one activity. But when i see reports thru CN41/ CN41N, this WBS-01 cost showing more than i have considered in Project Cost Plan so i check the breakdown of the WBS in the same report which shows only one activity and the cost is correct but varying in WBS. Seems this is an error.

Joefil C. Jocson
من قبل Joefil C. Jocson , CEO/President , Dyas Construction and Management Consultants

i think that WBS cost of250 is your budget, and you used only100 of it (in an Activity), that's why when you generate a cost report in CN41 it shows that way. -- based from your description.