While executing the project it becomes obvious that you're not going to hit your end date. The project may be delayed by at least two months...

 This may impact the start date of another project that was due to start right after yours completed. What type of float best describes this situation?

a. Total float

b. Project float

c. Free float

d. Slack float

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/16

Best answer is 

 

b. Project float