Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You have just completed your project activity, work package, and contingency reserve estimates. What have you created as a result of completing these estimates?

What have you created as a result of completing these estimates?

a. Bottom-up estimate

b. Cost budget

c. Cost baseline

d. Definitive estimate

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/17
Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

C. 

Cost baseline consists of estimated costs of activities/work packages and contingency reserves.

Answer should be 

 

c. Cost baseline

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.