Which of the following process is involved in developing an approximation of the costs of the resources needed to complete project activities?

A. Cost budgeting B. Cost control C. Cost estimation D. Activity Resource Estimation

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/02/14
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Cost estimation --------------------