Your developer has provided u with an estimate based on the “cost per line of code”. What type of estimate did the developer use to provide this?

 

information?

A. Parametric estimating.

B. Bottom-up- estimating.

C. Analogues estimating.

D. PERTestmating .

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/11/25
Md Fazlur Rahman
by Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Option A: Parametric estimating ...............................

(a) parameter estimating is the correct answer

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thanks for your question. Option A- Parametric Estimating.

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

i join my opinion to the expatriate answer A. Parametric estimating.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The appropriate answer is option A

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation and the answer is A - Parametric Estimating .