Reserve Analysis technique NOT used during _.?

A. Control Costs

B. Estimating Activity Duration

C. Estimate Costs

D. Determine Budget

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/05/05
Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The Convenient answer- Option B is not used during the Estimating Activity Duration.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. My answer is option B. 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Reserve analysis technique is used in all the options ( processes ) mentioned above.

Mr.Muhammad Farooq - Reserve Analysis technique is used in Control Cost process as well. This is used to monitor the status of contingency & management reserves to determine whether the same reserves will do or additional reserves are needed. 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - Option A

Explanation: Reserve analysis is used during Estimate Costs to calculate contingency buffers that apply to individual or group of activities. Reserve analysis is used during Determine Budget to calculate management contingency buffers that apply to the entire project. Reserve analysis is done during Activity Duration estimation in order to calculate duration buffers for individual or group of activities

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is B

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

 I Agree answers Option A

 