In an ideal situation resource leveling should be limited to activities with___?

 A. With zero float time. B. With negative float time. C. With positive float time. D. With critical float time E. On the critical path.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/02/21
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. With positive float time.