What is the term that is used when referring to the adjustment of task schedules in order to deploy human resource more effectively?

 A. Crashing. B. Smoothing C. Leveling. D. Fast tracking. E. Loading.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/05/08
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Leveling. ----------------------------------