Adeel Aslam's image  
Answer added by  Adeel Aslam, Finance Manager, Al Kareem Garden
6 years ago

Identify and label each wire before pulling through conduit into control panel and junction box. Pull pump power cables and control switch cables through connectors into ... See More

keerthy sp's image  
Answer added by  keerthy sp, Engineer, NASSER S. AL-HAJRI & PARTNERS CO
7 years ago

its a control panel, so we need the control signals only, the control signals are in Extra Low Voltage, so depends up on the resistance and signal transmission we used si ... See More

Abdeldjalil benhammou's image  
Answer added by  Abdeldjalil benhammou, ts maintenance, algerie telecome
8 years ago

During control panel installation it is necessary to be controlled with a single wire control wire because we need just phase to illuminate LED 

ISHFAQ AHMED's image  
Answer added by  ISHFAQ AHMED, Electrical and Instrument Technician, Al Nakheel Hygienic Paper Manufacturer LLC
8 years ago

due to more accurate control and simplicity ans well as security