A. Initial defined risks B. Schedule milestones C. Product acceptance criteria D. Stakeholders influence E. Initial cost estimates
alternative forms of energy. You have just completed the project scope changes, requested changes, and updates to the project scope management plan. Which of the followin ... See More
alternative forms of energy. You have just completed the project Scope Planning process and created the Scope management plan. However, upon review, you have determined t ... See More
a. Scope planning b. Scope definition c. Scope baselining d. Scope verification
A. Create the preliminary scope statement B. Develop the project charter C. Create the work breakdown structure D. Develop the project management plan
your client that the change has been made. What's the best form of communication to use for this? A. Formal verbal B. Formal written C. Informal verbal D. Informal w ... See More
A. The statement of work is prepared by the customer while the scope statement is developed by the project management team. B. A project scope statement can become a cont ... See More
You put the requested changes through change control and they are approved so you need to update the Scope Statement to include the new work. Where can you find the most ... See More
A. Omit problems from the conference report. B. Ensure that changes to the project character are reflected in the definition. C. Verify the project schedule is on track. ... See More