Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following is the correct order of the Monitoring & Controlling processes for Scope Management?

<p>First Verify Scope, then Control Scope</p> <p> </p> <p>First Control Scope, then Verify Scope</p> <p> </p> <p>Both happen simultaneously</p> <p> </p> <p>There is not enough information to decide</p> <p> </p>

user-image
Question added by Deleted user
Date Posted: 2014/09/09
فؤاد أحمد حسين
by فؤاد أحمد حسين , مدير , حكومي

The scope management knowledge area defines two processes in the monitoring and controlling process group. The first process, verify scope, is the formal process of accepting project deliverables. It provides a mechanism to verify that deliverables meet or exceed project requirements. The second process, control scope, is the process of managing the project’s status and any changes to the scope baseline. Let’s look at each of the proceses individually.The verify scope process provides the project manager with the formal process to classify deliverables as acceptable or unacceptable,,, Thank you

Salauddin Mohammad
by Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

Verify scope, then control scope.

Mohamed abdelsalam shabrawi
by Mohamed abdelsalam shabrawi , Regional Director for the Arab Republic of Egypt , african energy company

Sorry I am not aware

Hossam Maghrabi
by Hossam Maghrabi , Project management & BPM Consultant. , Freelancer

You need to know the difference between the two process! so you can know when to use it.

 

Verify Scope is performed with the client or customer at the end of the project or phase to verify that the product is complete, all requirements are met and that the product is ready to be delivered and get the client formal acceptance.

 

Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. The key benefit of this process is that it allows the scope baseline to be maintained throughout the project.

 

If you still need to know when you have to use each one please inform me, Good Luck

Mohammed Thiab
by Mohammed Thiab , Founder / Chief Consultant , MV Consulting

I would go with the first answer ... assuming the scope has already been identified and documented first

Zafar Ayub
by Zafar Ayub , Manager IT , IMGC Global

I think by only scope definition we’ll not find scope controlling area because scope is also depends some other values like requirements, project specifications or etc. Means only scope isn’t enough for controlling.

Mohammad Habboub
by Mohammad Habboub , Product Manager & Scrum Master , MenaITech

the first option is correct.

Abdul-Hameed Deeb Al-Sawadi
by Abdul-Hameed Deeb Al-Sawadi , IT Manager , Masaneed Commercial Group (MCG)

For Sure:

First Verify Scope, then Control Scope.

Faraz Shafiuddin Shafiuddin
by Faraz Shafiuddin Shafiuddin , Business Analyst , National Guard Health

Verification of Scope is followed by Controlling the scope. Unless you finalize the scope and product delivery you cannot start monitoring it!

Michel Samir Michel Michel
by Michel Samir Michel Michel , Projects Manager , Pharaohs of 6 October

Both happen simultaneously

Ahmed Montasser Hasan Ibraheem Farag
by Ahmed Montasser Hasan Ibraheem Farag , Project Manager , Rawafed Tech

First answer

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.