The Gantt Chart was the first simple visual device to maintain production control. It is essentially a bar graph with_ axis and _ axis.

(a)   Time on the horizontal; the activities to be scheduled on the vertical(b)   Time on the vertical; project completion on the horizontal(c)   Time on the horizontal; project completion on the vertical(d)   Time on the vertical; the activities to be scheduled on the horizontal(e)   Time on either; the activities to be scheduled on the other.

user-image
Question added by Vinod Jetley , Assistant General Manager , State Bank of India
Date Posted: 2015/05/12
FITAH MOHAMED
by FITAH MOHAMED , Financial Manager , FUEL AND ENERGY CO for transportion petroleum materials

(a) >>>>>>>>>>>>>  Time on the horizontal; the activities to be scheduled on the vertical

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

 

(a)

 

Reason : A Gantt chart is essentially a bar graph with time on the horizontal axis and the activities to be scheduled on the vertical axis.

       Hence from above discussion, we can infer that option (a) is correct

Georges Aref Chaoul
by Georges Aref Chaoul , Business Unit Director - Consumer Services , Kaizen Asset Management Services

(A)                                      Thank You.

Alex Al Yazouri
by Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

(a)   Time on the horizontal;>>>>>>>>>>>>>>>>>>>>>>>

the activities to be scheduled on the vertical