The customer has sent you a change request. The change is easy to complete & it doesn’t affect the project budget. What should you do first?

لقد أرسل لك العميل طلب تغيير. التغيير سهل تنفيذه ولن يؤثر على ميزانية المشروع. فماذا يجب أن تفعله أولاً؟

Evaluate the impacts on other project constraints تقييم التأثيرات على باقي قيود المشروع

Send the change request to the change control board ارسل طلب التغيير الى مجلس التحكم في التغيير

Make the change as soon as possible نفذ التغيير في أقرب وقت ممكن

Ask the project sponsor to approve the change request اطلب من راعي المشروع الموافقة على طلب التغيير

 

 

International trainer ENG . Hassan Shalaby

 

user-image
Question added by hassan shalaby , اخصائي تسويق ومبيعات، ومدرب مهارات معتمد من جامعة نوتنجهام بالمملكة المتحدة وجامعة عين شمس بالقاهرة , Galal Al , Sharif _Trading
Date Posted: 2017/01/03
asber shaabo
by asber shaabo , ادارة -محاسبة - متابعة شؤون الفندق لدى القطاع العام و الخاص , فندق عينكاوة باﻻص - فندق ارابيﻻ غراند -نقابة محامي كردستان العراق

The customer will send a request for a change in his order, whether in the quantity or quality of the product, I will deal with the available possibilities, which will benefit the company and the customer involved

Customer is first priority so such rule must be followed.

Yahya Bah
by Yahya Bah , Principal & Marketing Consultant , International Community

Th first thing to do is evaluate the impacts on other project constraints.

My answer is for the first option -- Evaluate the impacts on other project constraints

Faraz Shafiuddin Shafiuddin
by Faraz Shafiuddin Shafiuddin , Business Analyst , National Guard Health

Send the change request to the change control board ارسل طلب التغيير الى مجلس التحكم في التغيير

 

Get stakeholder approval before making any change and ensure it doesnt impact other business and technical areas. Also ensuring too many changes are not entertained at this stage by making stakeholders aware of the change management process and change control.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation & necessary information.

Inform all the concerned persons and stakeholders and accommodate the change as its not impacting budget.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Bater option is #1          -------------------------

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is "Evaluate the impacts on other project constraints"

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Ask the project sponsor to approve the change request

Ehsan Banat
by Ehsan Banat , Sales Manager , Kuwait Paint Co.

Evaluate the impacts on other project constraints