Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

All of the following statements are true except: ?

A. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of monitor and control project work process B. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are inputs of integrated change control process C. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of integrated change control process D. None of the choices are correct

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/15
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of integrated change control proce

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.