A. activity list..
B. work package .
C. WBS
D. cost account coding system.
(B work package is the correct answer
Thanks for the invite.
Most appropriate is B - Work Package
WBS is made up of many work components or work packages.
I seem B is good answer. Thank you mohammad.
Thanks for invite
I agree Mr mohamed asem
In my opinion --- C. WBS --------
------------ Option (B) Work Package -------------
Option b) Work Breakdown Structure - It is a deliverable-oriented grouping of project elements that organizes and defines the total scope of the project. It is a communication tool and it describes what needs to be done and what skills are required. Anything missing in the WBS should be added.