Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The scope baseline consists of which of the following elements?

a. Project management plan, WBS, scope statement

b. Scope statement, risk management plan, WBS

c. WBS dictionary, project management plan, scope statement

d. Scope statement, WBS, WBS dictionary

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/12
Javad Taghavi
by Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

PSS, WBS and WBS dictionary

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for your invitation...the answer is....d. Scope statement, WBS, WBS dictionary

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.